Phases and timeline

Below is a general timeline for project completion. Note that the commencement of the transition to a fully implemented budget model will begin in March 2027.

University community consultations, presentations and discussions will be woven into every phase of development.
 

Phase 

Action 

Timing 

Phase 1 

Explore alternative budget model approaches and make a recommendation to senior leadership 

Completed 

Phase 2 

Finalize governance and implementation structure and populate committees 

Completed July 2025 

Phase 3 

Design the conceptual model for the recommended approach 

July 2025-Nov. 2025 

Phase 4 

Model results and develop a transition 

Nov. 2025 -March 2027

Phase 5 

Develop tools, improve data quality, complete training and education 

Sept. 2025-March 2027

Phase 6 

Model implementation, training and shadow budget 

March 2027