Datacenter Sustainment Schedule & Milestones
Schedule is subject to delivery times
Schedule
| Date |
Description |
| May 29 |
Storage Arrives at MUN |
| June 4 |
South XIV Install Begins |
| June 8 |
Servers Arrive at MUN |
| June 11 |
North XIV Install Begins |
| June 12 |
New Server Installs Begin |
| June 15 |
South XIV Install Complete |
| June 19 |
North XIV Install Complete |
| June 24 |
New Server Installs Complete |
| June 25 |
SAN Switch Installs Begin |
| June 26 |
Server Virtualizations Begin |
| June 27 |
SAN Switch Installs Complete |
| July 20 |
Server Virtualizations Complete |
| July 21 |
Server Migrations Begin |
| August 21 |
Tape Backup Upgrade Begins |
| August 27 |
Tape Backup Upgrade Complete |
| August 28 |
Server Migrations Complete |
Milestones
| Date |
Description |
| April 30 |
New Equipment Ordered |
| June 19 |
Storage Upgrade Complete |
| June 24 |
Server Installations Complete |
| July 20 |
Server Virtualizations Complete |
| August 27 |
Tape Backup Upgrade Complete |
| August 28 |
Server Migrations Complete |
| August 28 |
Post-Implementation Review Complete |
| August 28 |
MUN Infrastructure Refresh Complete |