Schedule

Date Description
May 29 Storage Arrives at MUN
June 4 South XIV Install Begins
June 8 Servers Arrive at MUN
June 11 North XIV Install Begins
June 12 New Server Installs Begin
June 15 South XIV Install Complete
June 19 North XIV Install Complete
June 24 New Server Installs Complete
June 25 SAN Switch Installs Begin
June 26 Server Virtualizations Begin
June 27 SAN Switch Installs Complete
July 20 Server Virtualizations Complete
July 21 Server Migrations Begin
August 21 Tape Backup Upgrade Begins
August 27 Tape Backup Upgrade Complete
August 28 Server Migrations Complete

Milestones

Date Description
April 30 New Equipment Ordered
June 19 Storage Upgrade Complete
June 24 Server Installations Complete
July 20 Server Virtualizations Complete
August 27 Tape Backup Upgrade Complete
August 28 Server Migrations Complete
August 28 Post-Implementation Review Complete
August 28 MUN Infrastructure Refresh Complete