Datacenter Sustainment Schedule & Milestones

Schedule is subject to delivery times

Schedule

DateDescription
May 29Storage Arrives at MUN
June 4South XIV Install Begins
June 8Servers Arrive at MUN
June 11North XIV Install Begins
June 12New Server Installs Begin
June 15South XIV Install Complete
June 19North XIV Install Complete
June 24New Server Installs Complete
June 25SAN Switch Installs Begin
June 26Server Virtualizations Begin
June 27SAN Switch Installs Complete
July 20Server Virtualizations Complete
July 21Server Migrations Begin
August 21Tape Backup Upgrade Begins
August 27Tape Backup Upgrade Complete
August 28Server Migrations Complete

Milestones

DateDescription
April 30New Equipment Ordered
June 19Storage Upgrade Complete
June 24Server Installations Complete
July 20Server Virtualizations Complete
August 27Tape Backup Upgrade Complete
August 28Server Migrations Complete
August 28Post-Implementation Review Complete
August 28MUN Infrastructure Refresh Complete